PennDOT - District 6 News: U.S. 422 Reduced to Single Lane Next Week for Construction in Limerick Township

An update has been published to District 6 News on the PennDOT website. Please see below for details.

PennDOT - District 6 News

U.S. 422 Reduced to Single Lane Next Week for Construction in Limerick Township

King of Prussia, PA – U.S. 422 motorists will encounter a single lane closure in both directions next week for resurfacing and sign installation under a project to rehabilitate pavement and repair seven structures along a five-mile section of U.S. 422 between the Royersford/Trappe and Sanatoga interchanges in Limerick and Lower Pottsgrove townships, Montgomery County, the Pennsylvania Department of Transportation (PennDOT) announced today.

The work schedule is:

  • Sunday, September 20, through Friday, September 25, from 3:00 AM to 2:00 PM the following afternoon, alternating left and right lane closures will be in place on westbound U.S. 422 between Township Line Road and Evergreen Road and at the Limerick and Sanatoga interchanges; and
  • Monday, September 21, through Friday, September 25, from 10:00 AM to 8:00 PM, alternating left and right lane closures will be in place on eastbound U.S. 422 between Park Road and Township Line Road and at the Limerick and Sanatoga interchanges.

In addition, lane restrictions with flagging will occur on Upper Indian Head Road between Cider Mill Road and Winding Ridge Road in Upper Providence Township on Monday, September 21, through Friday, September 25, from 6:30 AM to 6:00 PM for bridge construction.

Motorists are advised to allow extra time when traveling through the work areas because backups and delays will occur. All scheduled activities are weather dependent.

Work on this project will be in accordance with Centers for Disease Control and state Department of Health guidance as well as a project-specific COVID-19 safety plan, which will include protocols for social distancing, use of face coverings, personal and job-site cleaning protocols, management of entries to the jobsite, special signage and relevant training.

Under this two-year improvement project, PennDOT's contractor will mill, overlay and rehabilitate existing U.S. 422 pavement; perform bridge deck repairs, concrete and joint patching, sealing and drainage improvements; install new guide rail and rumble strips; and repair or replace damaged traffic signs along the corridor.

H & K Group Inc. of Skippack, Montgomery County is the general contractor on the $19.1 million project which is financed with 100 percent federal funds. The entire project is expected to be completed in summer 2021. For information, visit www.422improvements.com.

For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery and Philadelphia counties, visit www.penndot.gov/District6TrafficBulletin.

Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com or downloading the 511PA application for iPhone and Android devices. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras.

Follow PennDOT on Twitter at www.twitter.com/511PAPhilly and like the department on Facebook at www.facebook.com/groups/phillypenndot and Instagram at www.instagram.com/pennsylvaniadot.

MEDIA CONTACT: Brad Rudolph, 610-205-6800

 

# # #