U.S. 1 (Roosevelt Expressway) Lane Closures at Night Next Week for Viaduct Rehabilitation in Philadelphia

King of Prussia, PA – Nighttime lane closures will be in place in both directions next week on U.S. 1 (Roosevelt Expressway) for construction on the Wayne Junction Viaduct over SEPTA tracks and the Nicetown neighborhood in North Philadelphia, the Pennsylvania Department of Transportation (PennDOT) announced today.
 
The work schedule is:

  • Monday, July 6, through Friday, July 10, from 6:00 PM to 5:00 AM the following morning, southbound U.S. 1 (Roosevelt Expressway) will be reduced to a single lane between the 16th Street and Fox Street overpasses; and
  • Monday, July 6, through Wednesday, July 10, from 9:00 PM to 5:00 AM the following morning, northbound U.S. 1 (Roosevelt Expressway) will be reduced to a single lane between the Fox Street and 16th Street overpasses.

Traffic in either direction also may be slowed periodically for equipment repositioning and other activities in the work area during the overnight construction. Motorists are advised to allow extra time when traveling on U.S. 1 (Roosevelt Expressway) through the work area because slowdowns and backups will occur. All scheduled activities are weather dependent. 

The contractor is currently rehabilitating and repainting the structural components and placing new concrete pavement on the center section of the half-mile-long viaduct.

Work on this project will be in accordance with Centers for Disease Control and state Department of Health guidance as well as a project-specific COVID-19 safety plan, which will include protocols for social distancing, use of face coverings, personal and job-site cleaning protocols, management of entries to the jobsite, special signing, and relevant training.

South State, Inc. of Bridgeton, N.J. is the general contractor on the $90.7 million project which is financed with 80 percent federal and 20 percent state funds. The entire project is expected to be completed in late 2022. For more information, visit www.us1wav.com.

Subscribe to PennDOT news and traffic alerts in Bucks, Chester, Delaware, Montgomery and Philadelphia counties at www.penndot.gov/District6.

Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com or downloading the 511PA application for iPhone and Android devices. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 950 traffic cameras.

Follow PennDOT on Twitter at www.twitter.com/511PAPhilly and like the department on Facebook at www.facebook.com/groups/phillypenndot and Instagram at www.instagram.com/pennsylvaniadot.

MEDIA CONTACT: Brad Rudolph, 610-205-6800


# # #

 US 1 Lane Closures Fox Street to 17th Street.jpg

Read More
Please note: you are receiving this email because you have subscribed to receive updates for District 6 News on the PennDOT website. To unsubscribe, or to find additional subscriptions available from the Commonwealth of Pennsylvania, please click the Manage Subscriptions link below.

Manage Subscriptions

No comments:

Post a Comment