PennDOT - District 6 News
I-95 Single, Double Lane Closures Scheduled Next Week for Construction in Delaware County
King of Prussia, PA – Interstate 95 motorists will encounter single and double lane closures in both directions next week at several locations between the Route 452 (Exit 2) and Edgmont Avenue (Exit 6) interchanges for various construction activities under a project to rehabilitate pavement and repair 15 structures on more than 11 miles of the interstate in Lower Chichester, Upper Chichester, Chester, Ridley and Tinicum townships, the City of Chester and Upland and Ridley Park boroughs, Delaware County, the Pennsylvania Department of Transportation (PennDOT) announced today.
The work schedule is:
- Monday, August 16, through Thursday, August 19, from 7:00 PM to 9:00 PM and from 5:00 AM to 6:00 AM, a single lane closure will be in place on northbound and southbound I-95;
- Monday, August 16, through Thursday, August 19, from 9:00 PM to 5:00 AM the following morning, a double lane closure will be in place on northbound and southbound I-95;
- Friday, August 20, from 7:00 PM to 9:00 PM and from 7:00 AM to 9:00 AM, a single lane closure will be in place on northbound I-95; and
- Friday, August 20, from 9:00 PM to 7:00 AM the following morning, a double lane closure will be in place on northbound I-95.
Motorists are advised to allow extra time when traveling through the work areas because backups and delays will occur. All scheduled activities are weather dependent.
Under this project, PennDOT's contractor will mill, overlay and rehabilitate the existing concrete pavement including 41 ramps; perform minor structural repairs to 15 of the 33 bridges located in the project limits; repair sections of median barrier; upgrade guide rail; install new pavement markings, delineators and rumble strips; repair and clean existing inlets and pipes; and replace damaged or missing traffic signs. The Pennsylvania Welcome Center just north of the Delaware state line also will be improved with concrete base repairs and new parking stripes, pavement markings and signs.
Allan A. Myers, Inc. of Worcester, Montgomery County is the general contractor on the $68.4 million project, which is financed with 80 percent federal and 20 percent state funds. The entire project is expected to be completed in late 2023.
Motorists can check conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.
For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery and Philadelphia counties, visit www.penndot.gov/District6TrafficBulletin.
Information about infrastructure in District 6 including completed work and significant projects, is available at www.penndot.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.
Follow PennDOT on Twitter at www.twitter.com/511PAPhilly and like the department on Facebook at www.facebook.com/groups/phillypenndot and Instagram at www.instagram.com/pennsylvaniadot.
MEDIA CONTACT: Brad Rudolph, 610-205-6800
# # #